Background:
Since 2009 MN DOT started implementing Primavera P6 for scheduling to cover scoping, design and construction of highway projects.
Scope:
MN Best performed P6 CPM schedule review on Design-Build project ($16 million) with cost loaded schedules. Baseline and updates were reviewed for specification compliance, sequestered float, and general best practices. Additionally, MN Best Scheduler worked with MN DOT Tracks to confirm activities versus diaries and to process payment vouches. As part of this contract, MN Best worked on documentation of the process of lump sum payouts on a cost loaded schedule and general best practices for schedule management.
Key Project Personnel:
Chris Thomas (Project Controls Specialist Senior)